One Bartholomew Close

  • ContractorMace

  • Architect – Sheppard Robson
  • DeveloperHelical Bar

  • Sector – Commercial

  • Value£5.2 million

  • Completed – Yes

  • Duration – 42 Weeks
  • Client Requirements – Phase 2 consisted of the demolition of the existing building and the construction of a new 12 storey, 223,000sq ft office block, known as One Bartholomew Close.

  • ScopeFurniture, fittings & equipment Installation of WC IPS Panelling, cubicles, vanity units and mirrors. Factory lacquered door sets and wall panelling. Shower & changing room fit out. Back of house joinery fit out. Installation of brass patinated panels and Rimex column encasements

  • Details – A change in project client during the initial construction phase of the project meant a very tight schedule to continue to meet the original completion date set.

    Completion on time was achieved by the commitment of the Atlantic team and a strong supply chain supporting shorter lead times to reach key milestones.